Karuah National Park Erosion Repairs & Sign Installation


Karuah National Park, NSW

Overview

 BEEP was engaged by NSW National Parks and Wildlife Service to carry out erosion repairs, trail reinstatement, slope stabilisation, and signage installation across multiple sites in Karuah National Park. 


Works were focused along the Karuah River and at the Double Wharf Picnic Area trail, with a strong emphasis on preserving natural features and managing sensitive access conditions. 

About this Project

 Client: NSW National Parks and Wildlife Service
Capability: Erosion Control / Trail Works / Signage Installation
Location: Karuah National Park, NSW
Duration: 3 weeks 

Get in Touch

Scope of Work


  • Reinstatement of 70m of trail with imported material
  • Reforming of mitre and table drains with geofabric and gabion rock lining
  • Placement and compaction of over 100 tonnes of 100mm minus and 40mm scalpings
  • Construction of 3 new rollovers for drainage
  • Remediation of 6 eroded slopes across 3 sites
  • Manual material placement in steep, limited-access areas
  • Stabilisation of 750m² of slope with jute mesh and coir logs
  • Planting of approximately 1,400 Lomandra tubestock for erosion control
  • Installation of 10 new signs using excavator with auger and concrete footings
  • Dyna-bolting of signage to existing sandstone logs where required

Summary

 The Karuah Erosion Repairs and Signage project was delivered safely and within a 3-week window, despite weather delays and challenging access conditions. 


BEEP successfully stabilised slopes, restored key trail infrastructure, and installed directional signage throughout the park. 


The site was handed back clean, stable, and future-proofed against erosion and storm events, with coir logs and revegetation left in place to support long-term environmental outcomes. 

    Related Projects

    Little River - Concrete Fire Trail

    Little Mountain Rd, Karuah National Park

    Little Mountain Rd, Karuah National Park

    Upper Myall, NSW

    Little Mountain Rd, Karuah National Park

    Little Mountain Rd, Karuah National Park

    Little Mountain Rd, Karuah National Park

    Karuah, NSW

    Copyright © 2025 ^Brown Environmental Earthworks Planning Pty Ltd - All Rights Reserved.


    Contact:  0410 436 968    |    info@beepservices.com.au

    • Home
    • Blog
    • Contact Us
    • Who we are
    • What we do
    • Our Projects