Rocky Point, NSW
BEEP was engaged by Central Coast Council to deliver saltmarsh rehabilitation works at Rocky Point. The foreshore was excavated and reshaped, mulched with seagrass wrack, and planted out with saltmarsh species. Erosion controls were put in place and the site is now stabilised, providing habitat for shorebirds and long-term protection against erosion.
Client: Central Coast Council
Capability: Saltmarsh Rehabilitation / Erosion Control
Location: Rocky Point, NSW
Duration: 4 weeks
Value: $511,000
Approx. 400m² of saltmarsh established and 60m of foreshore stabilised. 5,800 plants installed with an 80% survival rate.
Habitat created for shorebirds and erosion risks addressed. Site handed back in June 2023, clean and resilient with controls in place for ongoing weed management.