Swansea Heads, NSW
BEEP delivered staged seawall remediation works at Swansea Heads, responding to significant washout and storm damage identified along the southern seawall and Lucy’s Groyne.
The project was delivered in two phases, including initial emergency works using surplus armour rock, followed by engineered reconstruction based on coastal design advice from Salients Coastal Engineers. Works were carried out adjacent to sensitive parkland and foreshore assets with careful environmental management and access control throughout.
Client: NSW Crown Lands
Capability: Rock Revetment / Coastal Resilience
Location: Swansea Heads, NSW
Duration: 15 working days
The 15-day construction program restored 290 linear metres of rock revetment, including Lucy’s Groyne and adjoining foreshore areas.
With a combination of staged reconstruction, imported sand backfilling, and full landscaping restoration, the project met all design and environmental specifications. Community feedback was overwhelmingly positive, with park users noting the improved safety, appearance, and resilience of the repaired seawall.